Madera, Merced farm bureaus say state rail agency is violating farmland settlement
Watch Tuesday’s groundbreaking ceremony live here.
The Madera and Merced county farm bureaus allege that the California High-Speed Rail Authority is falling short of its responsibilities under a legal settlement stemming from the organizations’ lawsuits over the Merced-Fresno portion of the statewide bullet-train route.
The notice of default, in a letter from the farm bureaus’ attorney Jason Holder to the rail agency, came on the eve of Tuesday’s formal groundbreaking for the initial construction of the controversial project. The farm organizations’ lawsuit was filed in mid-2012, after the rail authority’s board approved much of the 60-mile Merced-Fresno route. It was one of several lawsuits challenging the authority’s environmental analysis of the section, all of which were settled by the spring of 2013.
Among the key provisions of the April 2013 settlement was a requirement that the rail authority make up for the loss of farmland to the railroad right of way by providing permanent preservation of similar-quality farmland elsewhere in the region. The authority was also to offer to buy any leftover parcels under 20 acres when the rail line divides an owner’s property.
Monday’s notice asserts five specific violations of the settlement, by either the rail authority or its right-of-way contractors, related to appraising and buying the property it wants for the right of way:
Not having a consultation process for valuations “has resulted in appraisals that substantially underestimate the value of property that the authority proposes to acquire and the amount of severance damages to remainder parcels,” Holder, an Oakland attorney, wrote in the default notice. “The appraisals fail to take into account for landowner compensation the value of crops under cultivation … at the time the property is acquired.”
Madera County Farm Bureau president Al Sheeter was less subtle than the attorney. “They’re robbing us blind, it’s that simple,” Sheeter said in a written statement. “The appraisals leading up to the offers on properties in Madera County amount to theft of private property.”
The notice gives the rail agency 30 days to either solve the issues or else the farm bureaus would return to Sacramento County Superior Court to ask a judge for court orders to enforce the settlement. “Of course, we hope that the authority timely cures each of the defaults … so that judicial enforcement of the agreement can be avoided,” Holder wrote.
To date, the authority’s efforts to purchase property for the railroad route have focused solely on its first construction package, a 29-mile stretch from the northeast edge of Madera to the south end of Fresno.
The agency has acquired about 100 of the more than 500 pieces of property needed, either in whole or in part, to build the Madera-Fresno segment of the rail line and associated structures such as bridges and overpasses. Demolition work began last summer, and following Tuesday’s groundbreaking, major construction could commence within weeks.
This story was originally published January 5, 2015 at 5:32 PM with the headline "Madera, Merced farm bureaus say state rail agency is violating farmland settlement."