Visalia street work begins on Monday

The Fresno BeeMay 13, 2014 

Drivers in Visalia will begin experiencing lane closures as the city starts a series of road improvements that will last through the summer months.

Electrical work will begin Monday and continue through May 26, while concrete work starts Monday and will run through July 18 at various locations. One lane of traffic will be closed and one lane will remain open in each direction at the work sites.

The locations and anticipated dates of grinding and asphalt work are:

    Walnut Avenue from Cottonwood to Linwood streets and Akers Street from Cambridge to Wagner avenues, June 19-26.

  • Giddings Street from Walnut to Tulare avenues, July 1-3.
  • Court Street from Tulare to Sequoia avenues, July 9-10.
  • Main Street from Burke Street to Ben Maddox Way, July 15-16.
  • Demaree Street from Hillsdale to Goshen avenues, July 23-25.
  • Hurley Avenue from Atwood to Chinowth streets, July 30-31.

Concrete work will happen between 9 a.m. and 3 p.m. while school is in session, and from 6 a.m. to 2:30 p.m. during schools' summer break.

Project details: (559) 994-4502.

Check fresnobee.com for breaking news.

The Fresno Bee is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.

Commenting FAQs | Terms of Service