Delays may threaten Valley high-speed rail funds

- The Fresno Bee

Saturday, Oct. 06, 2012 | 11:24 PM

tool name

close
tool goes here
0 comments

"We moved that back specifically at the request of the bidders," Morales said. "They wanted more time to look at things and develop their responses, and, quite frankly, it's in our best interest."

The bid date is one key part of a series of steps involving engineering, buying property for right of way, preliminary work such as relocating utilities and, finally, rolling out the bulldozers for the heavy work of building the line.

The authority does not expect to award a contract until at least late February or early March of next year, giving its staff and consultants a couple of months over the holiday season to evaluate the bids.

Once the bids come in, the authority has six months to select a contractor, negotiate a contract and issue a notice for the contractor to start work.

Felker said the agency anticipates needing almost all six months to buy the property for the right of way. But the authority cannot start making offers to landowners until it gets a green light from the state Public Works Board -- and that is not expected until sometime next month.

The land-buying schedule "is very challenging," Felker said in the court document. If the authority hasn't made enough progress in buying property by late April, he added, "the contractor will be restricted in the work it can do."

In a separate court declaration, Patricia Jones, the authority's director of real property, said some property appraisals and investigations for hazardous materials could be done this fall and winter before any offers are made to landowners. The authority must buy all or part of about 400 parcels for the Madera-Fresno stretch.

But, she added, "the authority does not anticipate making any offers until December 2012 at the soonest, and these would likely be very few in number, if any" because of the holiday season.

Jones said the first offers are expected to be in Fresno, south of the San Joaquin River. On the Madera County side, north of the river, "the bulk of offers will not be made until March or April 2013," she said in the court document.

Cushion built in

Morales said the project is being bid as a "design-build" contract -- which means that the winning bidder will be expected to finish the engineering and design work that is now about 30% complete before starting on the construction.

That, he said, gives the authority a cushion for buying land and preparing for construction.

The authority needs to buy land before it can do site-preparation work to pave the way for the major work by the prime contractor, he added.

Still, according to court documents, "physical work such as hazardous material remediation, utility relocation and limited building demolition could take place prior to full-scale construction, but almost certainly" not before mid-May.

The rail authority hopes to be able to buy right of way from willing sellers. But some property owners have vowed to fight -- which will require the authority to go to court, parcel by parcel.

Unlike some court cases that can linger for months or years, however, "eminent domain is a well-understood process that has clear time frames attached to it," Morales said.

But recalcitrant land owners aren't the only potential hitches in an ambitious schedule.

The same drawn-out process of seeking and screening bids, awarding a construction contract, and making offers to buy property will need to play out on at least three more stretches of the route between Fresno and Bakersfield -- from Fresno to Hanford, Hanford to Wasco, and Wasco to Bakersfield. A fifth contractor will be responsible for laying the tracks for the entire 130-mile line from Madera to Bakersfield.

None of that can even start until the rail authority finishes its environmental review for the Fresno-Bakersfield section -- something that's not expected until at least 2013. And once it's approved, it is likely to face the same sort of legal challenges from opponents that have been lodged in suits over the Merced-Fresno section.

The authority's court documents in the Madera County lawsuit say contractors will be expected to complete work by October 2016. Short of an injunction that would halt the agency's work, Morales said, he believes the authority has enough cushion to beat the clock on the September 2017 federal grant expiration.

"Everything about this project is going to be aggressive," he said, "but we believe it's do-able."



The reporter can be reached at (559) 441-6319, tsheehan@fresnobee.com or @tsheehan on Twitter.

Similar stories:

  • Bid to block California high-speed rail work fails

  • Deadline extended again for high-speed rail bids

  • High-speed rail agency pushes back deadline for construction bids in Valley

  • Judge to consider high-speed rail injunction request

  • High-speed rail construction schedule pushed back

The Bee's story-comment system is provided by Disqus. To read more about it, see our Disqus FAQ page. If you post comments, please be respectful of other readers. Your comments may be removed and you may be blocked from commenting if you violate our terms of service. Comments flagged by the system as potentially abusive will not appear until approved by a moderator.